Channel on Jalan Petojo Barat Normalized

As many as 12 personnel of Gambir Sub-district Water Resources Executing Unit, Central Jakarta are normalizing the water channel alongside Jalan Petojo Barat, Petojo Utara Urban Village.

It is targeted to be complete within two weeks

"It has been ongoing since last week. We'll normalize the channel up to 125 meters using U-ditch. And now it has touched 40 meters," stated Gambir Sub-district Water Resources Executing Unit Head, Satino, Thursday (11/14).

It is hoped able to minimize inundation in the location during rainy season.

Gubuk Genteng River Normalization is Targeted to Finish in January

"It is targeted to be complete within two weeks," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1573 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1431 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1297 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1092 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye964 personDessy Suciati